Back to News & Updates

NEWS & UPDATES

construction updates

Stage 7D1 Construction Updates

2024-03-22

YourLand Developments is excited to inform purchasers within Stage 7D1 that Titles have now been received and settlements will occur in the coming weeks. We very much look forward to welcoming the newest residents to the River Valley community.

 

February 24′: Construction Update

Construction onsite has been charging ahead with the following works now complete:

  • Construction of lot front rock wall.
  • Planting of trees along the base of the rock wall.
  • Backfilling of landscape wall and planting of trees behind the landscape wall to follow.

Titles are still anticipated for March, and we would recommend you make contact with your broker/lender and conveyancer to begin the necessary preparations for Settlement.

December 23′: Construction Update

– Construction on the rock retaining wall is ongoing and progressing well.
– Installation of services is now underway with sewer, water, electricity and stormwater assets being extended past the front rock walls for each lot.

November 23′: Construction Update

– Construction on the rock retaining wall is ongoing and progressing well.
– Provisioning for the telecommunications (Opticomm) is now complete.
– Service connections for each lot will commence shortly. Following that, the rock retaining walls located at the front of the lots (where applicable) will be constructed.

October 23′: Construction Update

– The removal of topsoil and bulk excavation works in Stage 7D1 are now complete.
– Work is progressing well on the rock retaining wall at the rear of the lots.
– Construction of Stage 7D1 is progressing well.

Between now and the end of the year, the team onsite will continue construction on the rock retaining wall. At this stage, it may begin to feel like the retaining wall progress is slowing down. The engineering for these large retaining walls is precise and rock placement becomes more difficult as the wall gets taller.

Imagine a set of building blocks. As the stack becomes taller, placing each block takes a little bit longer because extra care is taken to ensure strength and stability. As a result the higher rows take a little longer, than the lower ones did, to complete.

September 23′: Construction Update

– The removal of topsoil and bulk excavation works in Stage 7D1 are now complete.
– Work is progressing well on the placement of the rockface in the retaining wall at the rear of the lots.

August 23′: Construction Update

– The removal of topsoil and bulk excavation works in Stage 7D1 are now complete.
– Work has begun placing the rock that forms the visible element of the retaining wall. (This is an exciting point in the construction of the retaining wall becasue you will now slowly start to see what the finished product is going to look like.)

July 23′: Construction Update

– The removal of topsoil in Stage 7D1 is now complete.
– Bulk excavation of Stage 7D1 is also now complete.

June 23′: Construction Update

– Bulk excavation of Stage 7D1 is now complete meaning we’re now able to start on the next stages of infrastructure delivery.
– The construction team has also been making good progress on the Stage 7D1 retaining wall, which will form a major structural part of this stage.

May 23′: Construction Update

– Completion of bulk earthworks has now been achieved and works are now progressing on retaining walls and infrastructure delivery. The completion of bulk earthworks is a major milestone for the project and is the piece of work with the most uncertainty. Upon completion of the bulk earthworks the project team is able to assess the current state of the project and can plan to move forward with a greater degree of certainty in relation to the delivery timeframes.

April 23′: Construction Update

– Bulk excavation is progressing well with drainage and sewer works to commence in the coming months
– Site preparation is progressing well in readiness for construction of the 7D retaining wall, that will commence in the coming weeks.

March 23′: Construction Update

– Bulk earthworks have been progressing well with expected completion targeted for next month.
– The next phase of construction is the commencement of the feature retaining wall, which is expected to commence in April.

Back to News & Updates